Hobart, October 2026 —BESIX Watpac has been selected as preferred tenderer for the Macquarie Point Stadium in Hobart, beating Webuild to enter exclusive negotiations with the Macquarie Point Development Corporation on the $1.13 billion multipurpose stadium project.
The builder’s selection follows a Stage 1 evaluation that commenced after expressions of interest opened in January 2026. BESIX Watpac and Webuild were shortlisted in April from the initial field of respondents.
The firm will now negotiate a final price with Macquarie Point Development Corporation over the next two months, with a fixed-price contract expected to be signed in December.

Procurement Milestone for Macquarie Point Stadium
A final cost for the Macquarie Point Stadium is yet to be determined. The project has a $1.13 billion budget, though this figure has not been publicly updated since late 2025.
Negotiations over the next two months will determine final pricing before the fixed-price contract is executed in December.
BESIX Watpac operates in Australia and New Zealand as a stadium and venue builder, having delivered more than 60 stadiums and venue facilities across both markets. The firm was recently named joint delivery partner for the Brisbane Olympic Stadium build alongside John Holland Group.
Tasmanian Premier Jeremy Rockliff said the selection represented an important step for the state.
“We have searched the globe to find the best possible builder for our Macquarie Point Stadium. This moment cannot be understated – we are on the cusp of delivering thousands of jobs, injecting billions into our economy and creating a precinct that every single Tasmanian can be proud of” said Rockliff.
“Activity will soon increase at the precinct, bringing with it opportunity and activity the likes of which Hobart has never seen before. Over the coming month the Watpac team will continue to work with the Macquarie Point Development Corporation to finalise details to inform the delivery of this project. Let’s get on with it.”

Two-Stage Tender Process and Evaluation
Minister for Macquarie Point Urban Renewal Eric Abetz said the tender submission had been subject to comprehensive assessment.
“The critical preparatory works are underway, there are diggers in and the vision is beginning to come to life. The submission received has been subject to a comprehensive evaluation process involving subject matter experts, technical specialists, advisers, commercial experts and multiple layers of governance and probity oversight.”
The Stage 1 evaluation followed an earlier expression of interest process that shortlisted proponents to participate in the tender.
The Stage 2 process will allow further refinement of project delivery and continued engagement with local industry before any final decision on contract award is made.
“The Macquarie Point Stadium will significantly boost tourism, it will boost economic activity, it will deliver jobs, training and a future for so many Tasmanians.
It will be the first thing that greets people as they enter our capital city – a bustling waterfront precinct that is the envy of the nation. We are getting on with the job of delivering for Tasmania, we cannot wait to see this stadium coming out of the ground” said Abetz.

Early Works Underway, Completion Scheduled for 2030
Macquarie Point Development Corporation is the statutory authority responsible for overseeing the planning and delivery of the multipurpose stadium.
The stadium will have 23,000 seats, be roofed and serve as the home ground for the Tasmanian Devils AFL team. The stadium is a condition of Tasmania’s entry into the AFL, with the Devils set to debut in 2028.
Bulk earthworks began in July, with Tasmanian company Hazell Brothers leading site preparation and archaeological investigations through to mid-2027.
Construction is scheduled to finish in December 2030, with the stadium not expected to host AFL games until 2031.
Macquarie Point Development Corporation is charged with planning, facilitating and managing the remediation and development of Macquarie Point in Hobart. Macquarie Point will be a mixed-use precinct offering destinations and experiences as part of the 30-Year Greater Hobart Plan.

Note: The information presented in this article is for general informational purposes only and should not be relied upon as legal, financial, or professional advice. While we make every effort to fact-check and verify the information presented, we cannot guarantee its accuracy or completeness. Readers are encouraged to independently verify any information they find on our website and to consult with relevant professionals before making any decisions based on the information presented. The Australian Development Review does not own the rights to the information included within this article, and furthermore, there is no infringement intended from the included text and images within.